#57 stone (also written “57 stone”, “number 57 gravel” or “#57 crushed stone”) is the most common construction gravel in the United States: angular crushed rock between 3/4″ and 1″ with the fines screened out. Because it is clean and open-graded it drains fast, does not compact and is easy to shovel, which is why it shows up under concrete slabs, in French drains, on driveways and as pipe bedding. This calculator turns your area and depth into tons, cubic yards and truckloads, using the real density of #57 stone rather than a generic gravel number.
How to use the #57 stone calculator
- Enter the area
Length × width in feet for a driveway or slab, diameter for a round pad, or type the square footage directly. Add several areas together for a driveway with a parking spur.
- Set the depth
3–4″ for a driveway top course or drainage bed, 4″ under a slab, 6″ for a base on soft ground. In a French drain the depth is the gravel around the pipe – use the French drain calculator, which subtracts the pipe.
- Pick the stone
Limestone #57 is the default (105 lb/ft³). Granite and bluestone/trap rock #57 are a little heavier (110 lb/ft³), washed river gravel #57 and recycled concrete a little lighter.
- Read tons and truckloads
#57 is sold by the ton (sometimes by the yard). The ticket shows both, plus how many 10, 14 or 18-yard truckloads. Add a price per ton for the cost – and keep the waste allowance at about 5%, because clean stone does not compact.
#57 stone formula
Cubic yards = Length (ft) × Width (ft) × Depth (in) ÷ 324Tons = cubic yards × 1.42 · Coverage (sq ft per ton) = 2,000 ÷ (105 × depth in feet)
Example: 50 × 12 ft driveway, 4 inches of #57
- Area = 50 × 12 = 600 sq ft
- Volume = 600 × 4 ÷ 324 = 7.41 cubic yards
- Weight = 7.41 × 1.42 = 10.5 tons
- Add 5% for waste → order 11 tons – one tri-axle load
How much #57 stone do I need? Quick reference
| Area | 2″ deep | 3″ deep | 4″ deep | 6″ deep |
|---|---|---|---|---|
| 10 × 10 (100 sq ft) | 0.62 yd³ · 0.9 t | 0.93 yd³ · 1.3 t | 1.23 yd³ · 1.75 t | 1.85 yd³ · 2.6 t |
| 20 × 12 (240 sq ft) | 1.48 yd³ · 2.1 t | 2.22 yd³ · 3.15 t | 2.96 yd³ · 4.2 t | 4.44 yd³ · 6.3 t |
| 20 × 20 (400 sq ft) | 2.47 yd³ · 3.5 t | 3.70 yd³ · 5.25 t | 4.94 yd³ · 7.0 t | 7.41 yd³ · 10.5 t |
| 50 × 12 (600 sq ft) | 3.70 yd³ · 5.25 t | 5.56 yd³ · 7.9 t | 7.41 yd³ · 10.5 t | 11.11 yd³ · 15.75 t |
| 50 × 20 (1,000 sq ft) | 6.17 yd³ · 8.75 t | 9.26 yd³ · 13.1 t | 12.35 yd³ · 17.5 t | 18.52 yd³ · 26.25 t |
Limestone #57 at 105 lb/ft³ (1.42 tons per cubic yard). Figures exclude the 5% waste allowance.
Coverage: how many square feet does a ton of #57 cover?
One ton of #57 stone covers about 114 sq ft at 2 inches, 76 sq ft at 3 inches, 57 sq ft at 4 inches and 38 sq ft at 6 inches. The table below shows the figures for each variety.
| Material | Density | Tons per yd³ | sq ft per ton at 2" | sq ft per ton at 3" | sq ft per ton at 4" | sq ft per ton at 6" |
|---|---|---|---|---|---|---|
| #57 stone, limestone (3/4"–1") | 105 lb/ft³ | 1.42 | 114 | 76 | 57 | 38 |
| #57 granite | 110 lb/ft³ | 1.49 | 109 | 73 | 55 | 36 |
| #57 bluestone / trap rock | 110 lb/ft³ | 1.49 | 109 | 73 | 55 | 36 |
| #57 washed river gravel | 100 lb/ft³ | 1.35 | 120 | 80 | 60 | 40 |
| #57 recycled concrete | 95 lb/ft³ | 1.28 | 126 | 84 | 63 | 42 |
Coverage = 2,000 lb ÷ (density × depth in feet). Figures are for loose material; add 5–10% for waste and up to 20% for compacted base layers.
How much does #57 stone weigh?
Loose #57 limestone weighs about 105 lb per cubic foot, which is 2,835 lb (1.42 tons) per cubic yard. Granite and trap-rock #57 run 110 lb/ft³ (about 1.5 tons per yard); recycled concrete #57 about 95 lb/ft³ (1.3 tons per yard). Suppliers often round this to “1.4 tons per yard” or quote 0.7 cubic yards per ton – both match these figures.
What is #57 stone used for?
- Driveway top course – 3–4″ of #57 over a compacted base of larger stone. It stays loose, so it is not ideal as the only layer on a long driveway (use the driveway calculator for a proper three-layer build).
- Under concrete slabs and pavers – 4″ of #57 gives a capillary break and drainage; where you need a surface that compacts hard, use crusher run instead.
- French drains and foundation drains – the standard backfill around perforated pipe because water moves through it freely.
- Pipe and septic bedding, dry wells, retaining-wall backfill – anywhere you need drainage and no fines.
- Landscaping – paths, around AC units, decorative beds (though it is sharper underfoot than pea gravel).
#57 stone vs other gravel sizes
| Size | Particle size | Compacts? | Typical use |
|---|---|---|---|
| #3 / #4 | 1.5–2.5″ | No | Driveway base layer, heavy drainage, rail ballast |
| #57 | 3/4–1″ | No (clean) | Driveway top, slab base, French drains, pipe bedding |
| #67 | 3/4″ minus (clean) | No | Concrete aggregate, drainage – slightly finer than #57 |
| #8 / #89 | 3/8″ | No | Pea-gravel size, paver bedding (open-graded), asphalt |
| #411 / crusher run | 3/4″ minus with dust | Yes – 15–20% | Compacted bases for pavers, driveways, sheds |
| #10 / stone dust | Fines | Yes | Paver bedding, joints, path surface |
#57 stone cost
#57 limestone is typically $30–$60 per ton picked up at the quarry, with granite and trap rock at the higher end and recycled concrete #57 cheaper ($15–$35). Delivery adds $75–$150 for a full truck. Bagged #57 (0.5 cu ft, about 50 lb) costs $4–$7 a bag, which is $150–$250 per ton – only worth it for a very small job.
Frequently asked questions
How many tons of #57 stone are in a cubic yard?
About 1.4 tons (2,835 lb) for limestone #57; granite #57 is closer to 1.5 tons. One ton is roughly 0.7 cubic yards.
How much area does a ton of #57 gravel cover?
At 3 inches deep, one ton covers about 76 square feet; at 4 inches about 57 square feet; at 2 inches about 114 square feet.
How many tons of #57 stone do I need for a 50×12 driveway?
At 4 inches deep: 7.4 cubic yards, which is 10.5 tons – order 11 tons with a small waste allowance.
Does #57 stone compact?
No. It is clean, open-graded stone with no fines, so it interlocks a little when driven on but never packs into a hard surface. That is good for drainage and bad for a surface you want to stay smooth. If you want a hard-packed surface, use crusher run (#411) or 3/4″ minus and allow 15–20% for compaction.
How deep should #57 stone be for a driveway?
As a top course, 3–4 inches over a compacted base. As the only layer on firm ground, 4–6 inches. New driveways on soft soil need 4″ of larger #3/#4 stone underneath first.
What is the difference between #57 and #67 stone?
Both are clean 3/4″ stone. #67 has a slightly smaller top size (3/4″ down to about #4 sieve) and more small particles, so it packs a touch tighter; #57 runs 1″ to 3/4″. For drainage and driveways they are interchangeable.